Borehole drilling prices in South Africa: what a quote must itemise, and when the water needs registering
In short
Borehole drilling prices in South Africa are quoted per metre, by drilling method and diameter, with siting, casing, test pumping, water analysis, seals and the pump as separate lines. A factory or farm may take groundwater without a licence only within the 2016 general authorisation, and must register above an average of 10 cubic metres a day.
What work do you need done?
Headcore8 min read6 sources
How is borehole drilling priced per metre in South Africa?
In practice, drilling is priced per metre, with a separate rate for each method and diameter, and everything else is priced per borehole. Rustenburg Local Municipality's bill of quantities for tender RLM/DCD/0019/2024/25 covers drilling and equipping boreholes at its facilities over 36 months. It asks for a rate per metre for ODEX drilling at 194, 219 and 273 mm outside diameter, including ODEX casing with at least a 5 mm side wall, and for air percussion drilling at 194 mm.[5]
The depth and the diameter therefore drive the drilling line. In that schedule, the ODEX rate per metre includes the casing, while the air percussion line names no casing, so ask each driller what its rate includes.[5]
The Rustenburg schedule is published unpriced, so it shows what a public buyer pays for line by line, not the rates bidders offered. Ask every driller for the same lines, so the quotes can be laid side by side.[5]
What else is in the price besides drilling?
The Rustenburg bill of quantities prices drilling per metre and eight other borehole items per borehole or as a number of tests:[5]
| Line in the 2024/25 schedule | Unit | What it covers |
|---|---|---|
| Siting by a hydrologist before any drilling | Per borehole | Choosing where to drill |
| Drilling by ODEX or air percussion, by outside diameter | Per metre | The hole, with ODEX casing of at least 5 mm wall and a shoe |
| Test pumping to establish the yield | Per test | At least one full day of pumping, installing and withdrawing the test pump, and recovery measurements |
| Water samples tested in an approved laboratory | Per test | Chemical and biological analysis, reported to the engineer |
| Sanitary seal | Per borehole | Up to five metres, for the 194 mm casing |
| Concrete collar, disinfection and a lockable galvanised steel cage | Per borehole | Finishing and protecting the borehole |
| Capping of an unsuccessful borehole | Per borehole | Closing a hole that found no usable water |
| Pump, wiring and controls | Per pump | A pump rated for the duty, with its circuit breakers |
| Testing, putting into service and registration with the Department of Water and Sanitation | Per borehole | The paperwork that makes the water use lawful |
Sources:[5]
Do I need a water use licence for a borehole?
Not always, but a factory or farm needs an authorisation. Taking water from a borehole is "taking water from a water resource", a water use under section 21(a) of the National Water Act, 1998. Section 22(1)(a) allows it without a licence under Schedule 1, as an existing lawful use or under a general authorisation.[1]
Schedule 1 covers reasonable domestic use, small gardening that is not commercial and watering animals that graze the land (item 1(1)(b)). Process water for a plant or water for commercial irrigation therefore falls outside Schedule 1, under an existing lawful use, the general authorisation or a licence.[1]
General Notice 538 of 2 September 2016 sets the groundwater limit per property as its size in hectares multiplied by a rate for its drainage region, from 0 to 400 cubic metres per hectare a year (Appendix B, Table 2). The notice caps it at 40,000 cubic metres a year per property (paragraph 4.1).[2]
Where the drainage region's rate is 0, the notice allows no groundwater, which leaves a water use licence under section 22(1)(b) of the Act.[2][1]
The notice does not cover groundwater taken within 500 metres of a wetland or estuary, or within 100 metres of the riparian edge of a watercourse or a state dam. Nor does it cover groundwater within 500 metres of a state dam wall or of the ocean's high-water mark (paragraph 2.3).[2]
A user who takes more than an average of 10 cubic metres of groundwater a day over a year must register the use, and may take it only once registered. The use counts as registered when the department issues proof that the application was received (paragraph 7).[2]
Above 2 litres a second, the user must measure and record the volume taken at the end of each month and keep the records for at least five years (paragraph 6(2)).[2]
What is a yield test, and why does it matter?
A yield test pumps a new borehole under controlled conditions to establish how much water it can give, and the result sets the pump. The proposed groundwater regulations of December 2025 define borehole testing as pumping "under controlled test conditions in order to determine the performance characteristics of a borehole" (regulation 1). They define blow yield as the water blown out at each water strike during drilling.[3]
Under the proposal, a borehole used for abstraction would be tested according to SANS 10299-4 and fitted with a pump suited to the yield results (regulation 18(1)). The yield result or recommended sustainable abstraction rate would be lodged with the pump settings before abstraction starts (regulation 6(1)).[3]
Water quality is a separate test: the Rustenburg schedule prices chemical and biological analysis in an approved laboratory per sample, and the proposed regulations require laboratories accredited under ISO/IEC 17025 (regulation 21(3)). Water for drinking at a workplace must comply with SABS 241 (Facilities Regulations, 2004, regulations 1 and 7).[5][3][4]
What would the proposed 2025 groundwater regulations change?
The Minister of Water and Sanitation published proposed Regulations for the protection and management of groundwater resources for comment on 10 December 2025 (Government Notice 6935). By 15 November 2026 no final version had been published on gov.za, so the duties in this section are proposals and apply only once final regulations are published.[3]
The water user would have to appoint a driller registered on the National Groundwater Archive to manage the drilling (regulation 13) and obtain geosite identifiers from the archive before drilling (regulation 5(1)).[3]
The water user or driller would capture the drilling data on the archive within two months after the project closes (regulation 5(2)). Siting would follow SANS 10299-1:2003 or applicable best practice, with the geophysical data compiled into a geohydrological report (regulation 14).[3]
New boreholes would be built to SANS 10299 (regulation 15), and dry or unused boreholes closed off within 60 days of final use under SANS 10299-9 (regulation 16). Every groundwater user would install a meter on each borehole in use (regulation 20(2)).[3]
What does a borehole cost after it is drilled?
A borehole can carry municipal charges after it is drilled. The City of Mbombela's drainage and sewerage tariff schedule for 2026/27, approved on 29 May 2026, charges R877.12 for a business and R406.50 for a residence supplied through a borehole, and does not state a VAT basis.[6]
Water taken under the general authorisation may also be subject to water use charges under the national pricing strategy (General Notice 538, paragraph 8). The meter, its records and the pump's power are running costs of their own.[2]
Groundwater taken under the general authorisation may be used on another property (paragraph 4.1), which is how one site's borehole can supply another by water tanker hire.[2]
What to put in your request
- The property: erf or farm number, its size in hectares, and its distance to any wetland, river, state dam or the coast.[2]
- The use and volume: process, irrigation or drinking water, in cubic metres a day, and whether it will average more than 10 a day over a year.[2][1]
- Siting: who sites the borehole, by which survey method, and the report you will receive.[5][3]
- Drilling: a rate per metre for each method and diameter, the casing it includes and its wall thickness, and the expected depth.[5]
- A dry hole: what capping and closing off an unsuccessful borehole costs.[5][3]
- Test pumping: the duration, recovery measurements and a written sustainable yield, then a pump sized to that yield.[5][3]
- Water analysis in an ISO/IEC 17025 accredited laboratory, and SABS 241 results where the water will be drunk.[3][4]
- Completion: sanitary seal, concrete collar, disinfection, lockable cover and a water meter.[5][3]
- Paperwork: the drilling and geological log, and who registers the water use with the Department of Water and Sanitation.[5][2][3]
Questions buyers ask
Can a factory use borehole water without a licence?
Yes, within General Notice 538 of 2016: up to its property's size multiplied by its drainage region's rate, and at most 40,000 cubic metres a year. The borehole must lie outside the excluded buffers, and the use must be registered first above an average of 10 cubic metres a day. Beyond that, or where the region's rate is 0, it needs a water use licence.[2][1]
How do I register a borehole with the Department of Water and Sanitation?
Apply to the responsible authority to register the use. Under paragraph 7 of General Notice 538, the department must acknowledge receipt within 30 days, and the use counts as registered once it has issued that proof of receipt.[2]
What happens if the borehole is dry?
The hole still has to be closed safely and paid for. Rustenburg's 2024/25 schedule prices capping an unsuccessful borehole as its own line, and the proposed 2025 groundwater regulations would require dry or unused boreholes to be closed off within 60 days of final use under SANS 10299-9.[5][3]
Does the general authorisation last forever?
No. General Notice 538 runs for twenty years from the date it came into effect, unless withdrawn earlier, and its explanatory note says it may be withdrawn at short notice. A user who needs an entitlement with a firm duration may apply for a water use licence.[2]
What work do you need done?
Sources
- Government Gazette 19182, National Water Act 36 of 1998, 26 August 1998.
- Department of Water and Sanitation (Government Gazette 40243), General Notice 538 of 2016: revision of general authorisation for the taking and storing of water, 2 September 2016.
- Department of Water and Sanitation (Government Gazette 53828), Proposed regulations for the protection and management of groundwater resources (Government Notice 6935), 10 December 2025.
- Department of Labour (Government Gazette 26636), Facilities Regulations, 2004 (GN R. 924), 3 August 2004.
- Rustenburg Local Municipality, Bill of quantities and pricing schedule, RLM/DCD/0019/2024/25: drilling and installation of boreholes, water pumps and storage tanks at various facilities for 36 months, 2024/25 financial year (re-advertised).
- City of Mbombela, Tariff schedule for the 2026/2027 financial year: drainage and sewerage services, Approved 29 May 2026, effective 1 July 2026.