What is a baseline risk assessment under the Construction Regulations?

Baseline risk assessment: the risk assessment a client prepares for an intended construction work project, before the work starts, and on which it bases its site-specific health and safety specification.[1]

  • The client prepares a baseline risk assessment for an intended construction work project (regulation 5(1)(a)); it is the first duty in the client's list and the base of the health and safety specification (regulation 5(1)(b)).
  • It is the client's document. The contractor's risk assessments under regulation 9 are separate: a competent person appointed in writing performs them before and during the work, and they form part of the health and safety plan.
  • The Regulations do not define the term or set its format. A construction work permit application must include it, with the specification and the health and safety plan.

Headcore5 sources

What work do you need done?

Who must prepare a baseline risk assessment, and for which work?

The client. Regulation 5(1)(a) of the Construction Regulations, 2014 says a client must "prepare a baseline risk assessment for an intended construction work project". The Regulations were made under section 43 of the Occupational Health and Safety Act and published as Government Notice R. 84 in Government Gazette 37305 on 7 February 2014.[1][4]

The duty applies to construction work as the Regulations define it, which the Department of Labour's 2017 guidelines limit to building works and civil engineering works. The client is the person for whom the work is performed, so a company that contracts out a building repair at its own plant is the client.[1][2]

One exception: regulation 2(2) switches regulations 3 and 5 off where the construction work relates to a single-storey dwelling for a client who intends to live in it on completion. The client of that work prepares no baseline risk assessment under regulation 5.[1]

The Regulations do not define a baseline risk assessment or give it a format, and they name no qualification for drafting the document itself. What they do say is that the client prepares it for the intended project and bases the specification on it. A client may act through an agent, a competent person it appoints in writing as its representative, to whom the client's duties then apply as far as reasonably practicable; the client keeps its own health and safety responsibilities and liabilities (regulation 5(5) and (6)).[1]

How does it differ from the contractor's risk assessment?

The two are different documents with different owners. The client's baseline risk assessment comes first and feeds the specification; a contractor's risk assessments under regulation 9 follow, and sit inside the health and safety plan.[1]

How does it differ from the contractor's risk assessment?
QuestionBaseline risk assessmentContractor's risk assessment
Where it sitsRegulation 5(1)(a)Regulation 9(1)
Who prepares itThe clientA competent person appointed in writing, whom the contractor must have perform them
WhenFor an intended project, before the specification is preparedBefore the construction work starts and during it
What it feedsThe client's site-specific health and safety specification (regulation 5(1)(b))The health and safety plan to be applied on the site (regulation 9(1))
What the Regulations list in itNothing: no contents are listedIdentification of risks and hazards, analysis and evaluation by a documented method, a documented plan and safe work procedures, a monitoring plan and a review plan
ReviewThe Regulations state no review rule for itWhen design or construction changes alter the risk profile, or when an incident has occurred (regulation 9(7))

Sources:[1]

What happens to a baseline risk assessment after the client prepares it?

The client prepares a site-specific health and safety specification based on it (regulation 5(1)(b)), gives that specification to the designer (regulation 5(1)(c)) and makes sure the designer takes it into consideration during the design stage (regulation 5(1)(d)). The principal contractor's health and safety plan must be based on the specification (regulation 7(1)(a)).[1]

For larger projects it goes to the provincial director. Notice 850 of 2018, a temporary exemption from regulation 3(1) granted by the chief inspector, requires a construction work permit for work starting from 7 August 2018 that will exceed 365 days and involve more than 3,600 person days, or whose tender value limit is grade 7, 8 or 9 of the CIDB grading. A permit may be granted only if the fully completed documents in regulation 5(1)(a) and (b) have been submitted (regulation 3(5)(a)).[1][3]

Annexure 1, the permit application form, lists the baseline risk assessment among the documents submitted with it, beside the health and safety specification and the health and safety plan. The 2017 guidelines add a list of items to submit and tie the baseline risk assessment to regulation 3(5)(a) read with 5(1)(a).[1][2]

Construction work that does not meet those permit thresholds needs no permit. If it includes excavation, work at a height where there is a risk of falling, demolition or explosives, the contractor notifies instead: it sends Annexure 2 to the provincial director at least 7 days before work starts (regulation 4(1)). Outside the exception in regulation 2(2), the regulation 5 duty to prepare a baseline risk assessment applies to that work all the same.[1]

A worked example

A company plans an extension to its workshop that includes excavation for the foundations and steelwork at a height. As client, it prepares a baseline risk assessment for that project (regulation 5(1)(a)), writes a health and safety specification based on it and gives the specification to the designer. Suppose the work will not exceed 365 days, will not involve more than 3,600 person days and is not in CIDB grade 7, 8 or 9: no permit is needed, so the contractor notifies the provincial director on Annexure 2 at least 7 days before the work starts. The principal contractor's plan is then based on the specification, and its contractors' risk assessments follow under regulation 9.[1][3]

Questions buyers ask

Is a baseline risk assessment the same as a HIRA or a job risk assessment?

The Regulations use neither term. They name the client's document a baseline risk assessment. What a contractor has performed under regulation 9 are risk assessments by a competent person, forming part of the health and safety plan. These are separate duties with different owners, and the Regulations do not say one replaces the other.[1]

Does the client need an agent to prepare it?

Not as such. The duty in regulation 5(1)(a) is the client's. An agent, a competent person appointed in writing, is compulsory where a construction work permit is needed; where the work is notifiable the client may appoint one, and an inspector's decision on whether one is necessary is decisive (regulation 5(5) and (6)). The client keeps its responsibilities and liabilities either way.[1]

Does a small job at an existing plant need one?

Only if it is construction work as the Regulations define it, which the Department's 2017 guidelines limit to building works and civil engineering works. A repair to a building at a plant can be; other work is outside the Regulations. Check the work first, then the duty.[1][2]

Will the Construction Regulations change?

A draft that would repeal them was published for public comment on 12 March 2025 (GN 5983, Government Gazette 52267). Until a final text is gazetted, the 2014 regulations apply, with the permit triggers of Notice 850 of 2018.[5][1][3]

What work do you need done?

Sources

  1. Department of Labour (Government Gazette 37305), Construction Regulations, 2014 (GN R. 84), 7 February 2014.
  2. Department of Labour (Government Gazette 40883), Construction Regulations, 2014: Guidelines (GN 489), 2 June 2017.
  3. Department of Labour (Government Gazette 41839), Notice regarding application for construction work permit of construction work in terms of the Construction Regulations, 2014 (Notice 850), 17 August 2018.
  4. Government Gazette 14918, Occupational Health and Safety Act 85 of 1993, 2 July 1993.
  5. Department of Employment and Labour (Government Gazette 52267), Construction Regulations, 2024: invitation of public comments on the draft Construction Regulations (GN 5983), 12 March 2025.