Scaffold tagging in South Africa: who inspects a scaffold, how often, and what the tag and register must show
In short
Scaffold tagging shows whether a scaffold may be used: a green tag goes on once a competent inspector has passed it and recorded the inspection. In South Africa, the Construction Regulations, 2014 require temporary works, which include scaffolds, to be inspected at least daily and after inclement weather. Public clients' specifications differ, so put the interval in writing.
Tell us what scaffolding you need
Headcore7 min read10 sources
What is scaffold tagging?
Scaffold tagging is the sign on a scaffold's access point that tells workers whether the scaffold has been inspected and may be used. The South African unit standard for scaffold inspectors names three items of scaffold documentation and signage under SANS 10085: the inspection register, the handover certificate and the green tag.[7]
Public clients write the tag into their site rules. The South African Reserve Bank's December 2021 tender specification says an erected scaffold "may only be accessed when the green tag is displayed". The same document wants the register updated, and signs displayed, once the scaffold is declared safe to use.[8]
The tag is the visible end of an inspection system that runs from the erector to the register. Whoever supplies the scaffolding hire erects the scaffold. The regulations decide who may pass it for use and how often it is checked again.[1][7]
Which law sets scaffold inspection in South Africa?
Two regulations in the Construction Regulations, 2014 set it. Regulation 16(2) makes a contractor using access scaffolding ensure that, in use, it complies "with the safety standards incorporated for this purpose" under section 44 of the Act.[1]
Section 44(1) of the Occupational Health and Safety Act lets the Minister incorporate a standard by its number, title and year. Under section 44(4), the notice then refers to the standard as later amended or substituted, unless it says otherwise.[3]
The Department of Labour's 2017 guidelines to the Construction Regulations add a note to regulation 16: "Scaffolds must comply with SANS 10085". Under the 2003 regulations, Government Notice R. 1020 of 18 July 2003 incorporated the SABS 085 scaffolding code of practice, "as amended", for regulation 14(1).[2][4]
The Construction Regulations, 2014 repealed the 2003 regulations (regulation 34(1)). The current edition of the standard is SANS 10085-1:2026 (Ed. 2.01), approved on 12 August 2026, which replaced the 2024 edition.[1][6]
The second regulation is regulation 12 on temporary works. The 2014 regulations count a scaffold as temporary works (regulation 1). The 2017 guidelines add that, for regulation 12, scaffold design means design in terms of SANS 10085.[1][2]
How often must a scaffold be inspected?
A scaffold must be inspected at least daily. Regulation 12(3)(f) of the Construction Regulations, 2014 requires a competent person to inspect temporary works "after inclement weather or any other imposed load and at least on a daily basis".[1]
The inspections run until the structure is removed, with the results "recorded in a register and made available on site". Under regulation 12(3)(e), a competent person must also check all equipment for suitability before it is used.[1]
Before first use, regulation 12(1) requires a temporary works designer, appointed in writing, "to design, inspect and approve the erected temporary works on site before use". The 2017 guidelines say one person or different persons may hold these three functions.[1][2]
How often do South African public clients ask for scaffold inspections?
South African public clients ask for anything from daily inspections (the Reserve Bank's 2019 guidelines) to weekly ones (the Department of Health's 2025 scope of works). Agree the interval in the contract.[9][10]
| Document | Inspection interval | By whom | Basis the document gives |
|---|---|---|---|
| Construction Regulations, 2014, regulation 12(3)(f) | At least daily, and after inclement weather or any other imposed load | A competent person | Applies to all temporary works structures, which include scaffolds |
| South African Reserve Bank, health and safety specification guidelines (Revision 4, 2019) | Daily | A competent scaffolding inspector | Cites section 12(f) of the 2014 Construction Regulations |
| National Department of Health, scope of works NDoHF03-2025/2026 (December 2025) | Weekly | A scaffold inspector, after sign-off by a competent erector | States no regulation for the interval |
What do the green, yellow and red scaffold tags mean?
In practice, the green tag is the only colour the South African documents read for this page define: it marks a scaffold that is inspected and may be used. The inspector unit standard and the Reserve Bank's 2021 specification name no other colour.[7][8]
Yellow and red tags are site rules, so their meaning differs from one site to the next. Ask the scaffold contractor for its tag legend in writing, and make sure the site's induction uses the same one.[7][8]
The Reserve Bank's 2021 specification also limits who may change a tagged scaffold. Only scaffold erectors may alter its layout. No part may be removed for access unless the scaffold inspector and the construction manager approve it, signs warn of the danger and the workers on that part wear anchored harnesses.[8]
Who may inspect a scaffold in South Africa?
A scaffold inspector must be competent, and the contractor's appointed scaffolding supervisor carries that duty. Regulation 16(1) requires the contractor to appoint a competent person in writing. That person must ensure that "all scaffold erectors, team leaders and inspectors are competent to carry out their work".[1]
A competent person has the knowledge, training, experience and, where applicable, qualifications for the task (regulation 1). Training registered under the National Qualifications Framework Act, 2000 counts as the required training.[1]
The registered unit standard for the role is 263205, Inspect access scaffolding, at NQF level 4; its last date for enrolment is 30 June 2028. The scaffold hire or buy page sets out the related erector and supervisor standards.[7]
What must the scaffold contractor hand over to the client?
In practice, the client should receive a signed handover certificate, the inspection register and, for a specially designed scaffold, an engineer's certificate. The inspector unit standard expects the register and certificate to be completed and signed off after every inspection and re-inspection. It also expects engineer's certificates or reports for special design scaffolds.[7]
The National Department of Health's 2025 scope of works puts scaffolding tags in the health and safety file handed over at completion. The same file holds risk assessments, inspection checklists and operator licences.[10]
The client keeps a duty of its own. Under regulation 5(1)(s) of the Construction Regulations, 2014, the client must ensure that the principal contractor keeps and maintains that file.[1]
The draft Construction Regulations published for comment on 12 March 2025 would keep only the standards duty in their scaffolding regulation (draft regulation 16(1)). Until a final text is gazetted, the 2014 regulations apply.[5][1]
What to put in your request
- The scaffold's purpose, height, length of face and load: people only, or materials as well.[7]
- Compliance with SANS 10085-1:2026 (Ed. 2.01), and design by a temporary works designer appointed in writing under regulation 12(1).[6][1]
- The inspection interval in writing: at least daily under regulation 12(3)(f), and after inclement weather, an imposed load or any alteration.[1][7]
- Who inspects: the name of the competent person appointed under regulation 16(1) and proof of each inspector's competence, such as unit standard 263205.[1][7]
- A signed handover certificate and the inspection register at handover, kept on site and updated after every inspection.[7][1]
- The tag legend in writing: what green means, and what the site's other colours mean.[8]
- Who may alter the scaffold and who approves removing any part of it.[8]
- An engineer's certificate or report for a specially designed scaffold.[7]
- The tags, registers and certificates to be handed over in the health and safety file at completion.[10][1]
Questions buyers ask
Is SANS 10085 law in South Africa?
Regulation 16(2) of the Construction Regulations, 2014 requires scaffolding to meet the standards incorporated under section 44 of the OHS Act. The Department of Labour's 2017 guidelines state that "Scaffolds must comply with SANS 10085". The incorporation notice found for this page, R. 1020 of 2003, belongs to the repealed 2003 regulations.[1][2][4]
Does a scaffold need re-inspecting after rain or wind?
Yes. Regulation 12(3)(f) of the Construction Regulations, 2014 requires a competent person to inspect temporary works, scaffolds included, after inclement weather or any other imposed load. The daily inspection continues as well, with the results recorded in a register on site.[1]
Can the client's own staff inspect a hired scaffold?
Only if they are competent for the task. Regulation 16(1) places the scaffolding duties on the contractor, whose appointed competent person must ensure every inspector is competent. A client that wants its own inspector to sign the register should agree it with the contractor in writing.[1]
Tell us what scaffolding you need
Sources
- Department of Labour (Government Gazette 37305), Construction Regulations, 2014 (GN R.84), 7 February 2014.
- Department of Labour (Government Gazette 40883), Construction Regulations, 2014: Guidelines (GN 489), 2 June 2017.
- Government Gazette 14918, Occupational Health and Safety Act 85 of 1993, 2 July 1993.
- Department of Labour (Government Gazette 25207), Incorporation of Safety Standards in the Construction Regulations, 2003 (GN R. 1020), 18 July 2003.
- Department of Employment and Labour (Government Gazette 52267), Draft Construction Regulations: invitation of public comments (GN 5983), 12 March 2025.
- SABS Standards Division, SANS 10085-1:2026 (Ed. 2.01), The design, erection, inspection, use, modification and dismantling of steel access scaffolding and working platforms, Part 1: General (store entry), 12 August 2026.
- South African Qualifications Authority, Unit standard 263205: Inspect access scaffolding, Registered 1 July 2018 to 30 June 2023; last date for enrolment 30 June 2028.
- South African Reserve Bank, Annexure K1: Construction health and safety tender specification, GW176 SARB head office extension (demolitions), Revision December 2021.
- South African Reserve Bank, Annexure K2: Occupational health and safety specification guidelines (Revision 4/2019), Revision 4, 2019.
- National Department of Health, Scope of works NDoHF03-2025/2026: fabrication and erection of a steel water tank at Dysselsdorp Clinic, Last amended 9 December 2025.