What is a health and safety file on a South African construction site?
Health and safety file: a file or other record of the written information the Construction Regulations, 2014 require, which the principal contractor and each contractor must open and keep on site with the documents the Act requires.[1][3]
Also called Safety file
- The principal contractor opens and keeps a health and safety file on site, and each contractor opens and keeps its own before it performs any construction work (regulations 7(1)(b) and 7(2)(b)).
- The client keeps no file of its own under the regulations: it makes sure the principal contractor keeps and maintains one, and receives a consolidated file with drawings, designs and materials used when the work is complete.
- For the principal contractor's file, the regulations name an inspector, the client, the client's agent and a contractor as those who may ask to see it; a breach of regulation 7 is an offence.
Headcore5 sources
What work do you need done?
Who must keep a health and safety file?
The principal contractor and every contractor. A principal contractor must "open and keep on site a health and safety file" (regulation 7(1)(b)), and a contractor must do the same before it performs any construction work (regulation 7(2)(b)). The Regulations define the file as "a file, or other record containing the information in writing required by these Regulations" (regulation 1).[1]
A contractor that appoints another contractor takes on the principal contractor's duties in regulation 7(1)(b) to (g) as if it were the principal contractor (regulation 7(3)). The Regulations do not use the word sub-contractor; the Department of Labour's 2017 guidelines note that a contractor includes an organisation or self-employed person that contracts with a client, a principal contractor or a contractor to carry out construction work.[1][2]
The client does not open a file. Under regulation 5(1)(s), it must ensure that the file in regulation 7(1)(b) "is kept and maintained by the principal contractor". Regulation 2(2) switches regulations 3 and 5 off for a single-storey dwelling that the client will live in, and names no other regulation, so regulation 7 still applies to that work.[1]
The duty belongs to construction work as the Regulations define it. The Department of Labour's 2017 guidelines limit that to building works and civil engineering works, to be read with the Regulations' definition of a structure. The Regulations apply to "all persons involved in construction work" (regulation 2(1)).[1][2]
What goes into a health and safety file?
Regulation 7(1)(b) says the file "must include all documentation required in terms of the Act and these Regulations". It gives no list, so the contents follow from what the Act and the Regulations require elsewhere. These are the items the Regulations tie to the file:[1]
- A copy of the construction work permit, where one was needed: the client must ensure the principal contractor keeps it in the file for inspection (regulation 3(6)), which that regulation words as the occupational health and safety file.[1]
- A comprehensive and updated list of all the contractors on site accountable to the principal contractor, the agreements between the parties and the type of work being done (regulation 7(1)(f)).[1]
- The written appointment of each contractor the principal contractor appoints, for the part of the project on the construction site (regulation 7(1)(c)(v), which regulation 7(1)(f) counts among the documentation required in the file).[1]
- In practice, one national department's 2025 scope of works for a steel tank project describes the consolidated file handed over at completion as typically containing the risk assessments, incident reports, inspection checklists, scaffolding tags and operator licences compiled during construction. That is one client's document, not a rule of the Regulations.[5]
What does the client receive at completion?
The principal contractor must "hand over a consolidated health and safety file to the client upon completion of the construction work" (regulation 7(1)(e)). Beyond the documents in the contractors' files, it must include "a record of all drawings, designs, materials used and other similar information concerning the completed structure".[1]
That is the part a buyer can check at the end of a job: whether the consolidated file arrives, and whether the drawings, designs and materials used are in it.[1]
Regulation 7(1)(e) is one of the duties in regulation 7(1)(b) to (g) that regulation 7(3) applies to a contractor that appoints another contractor, as if it were the principal contractor.[1]
Who may ask to see the file, and who checks it?
The principal contractor's file must be made available on request to an inspector, the client, the client's agent or a contractor (regulation 7(1)(b)). A contractor's file must be made available on request to an inspector, the client, the client's agent or the principal contractor (regulation 7(2)(b)).[1]
The client's checks are its own duties under regulation 5(1): to ensure the file is kept and maintained (paragraph (s)), and to ensure audits and document verification run at least once every 30 days, with a copy of each audit report going to the principal contractor within seven days (paragraphs (o) and (p)).[1]
Breaching regulations 3 to 30 is an offence carrying a fine or imprisonment of up to 12 months, plus up to R200 or one day's imprisonment for each day a continuing offence goes on, the additional imprisonment capped at 90 days (regulation 33). Regulation 7 sits inside that range.[1][2]
A worked example
A company has a workshop extension built. It appoints a principal contractor in writing, which appoints an electrical contractor and a steel contractor. The principal contractor opens a file on site; each of the two opens its own before it starts work. The client does not keep one, but it checks that the principal contractor keeps and maintains it (regulation 5(1)(s)). If the steel contractor appoints a contractor of its own, the duties in regulation 7(1)(b) to (g) apply to the steel contractor as if it were the principal contractor (regulation 7(3)). At completion the principal contractor hands over the consolidated file with the drawings, designs and materials used.[1]
Questions buyers ask
Is a health and safety file the same as a health and safety plan?
No. The plan is "a site, activity or project specific documented plan" in accordance with the client's specification, which the principal contractor provides and demonstrates to the client and keeps updated as work progresses (regulations 1 and 7(1)(a)). The file is the record of the written information and documents the Act and the Regulations require, kept on site (regulation 7(1)(b)).[1]
Does a job outside construction work need a file?
The file duty sits in regulation 7 of the Construction Regulations, which apply to construction work. The Department's 2017 guidelines limit that to building works and civil engineering works. For other work, check whether the Regulations apply before asking a supplier for a file.[1][2]
Can the file be electronic?
The 2014 definition says "a file, or other record containing the information in writing", and does not name a medium. The Department's March 2025 draft replacement regulations, which have not been made, list the acceptance of electronic health and safety files among their key changes.[1][4]
Does the client need its own file?
The Regulations do not require the client to open one. Its duties are to ensure that the principal contractor keeps and maintains the file (regulation 5(1)(s)) and to receive the consolidated file on completion (regulation 7(1)(e)).[1]
What work do you need done?
Sources
- Department of Labour (Government Gazette 37305), Construction Regulations, 2014 (GN R. 84), 7 February 2014.
- Department of Labour (Government Gazette 40883), Construction Regulations, 2014: Guidelines (GN 489), 2 June 2017.
- Government Gazette 14918, Occupational Health and Safety Act 85 of 1993, 2 July 1993.
- Department of Employment and Labour, Employment and Labour invites public comments on repeal of Construction Regulations (media statement), 12 March 2025.
- National Department of Health, Scope of works NDoHF03-2025/2026: fabrication and erection of a steel water tank at Dysselsdorp Clinic, Last amended 9 December 2025.