What is wet hire, and how does it differ from dry hire?
Wet hire: hiring plant with the supplier's operator and fuel in the hire rate; in dry hire the hirer supplies the operator, and the fuel or a full tank on return.[1][6][3]
Also called Wet rate
- In wet hire the supplier's operator and fuel come with the machine, and in the South African municipal documents read for this page that ask for a wet rate, the supplier also carries maintenance or breakdowns.
- Documents differ on how much they say about dry hire: a 2020 municipal bid leaves operator and fuel to the hirer, a 2026/27 tariff says only that the machine goes out with a full tank and comes back with one, and a 2025 district tender names a dry rate inside its wet rate without defining it.
- A buyer should state in the request what each rate includes: operator, fuel, maintenance, insurance and transport.
Need one?TLB hire with an operatorPlant hire
Headcore7 sources
What work do you need done?
What is wet hire, and what is dry hire?
Wet hire is plant hired with its operator and fuel. George Municipality's 2020 plant hire bid described a wet rate as one where the contractor supplies the operator and fuel, and put the cost of labour, spare parts and lubricants for maintenance, servicing and repair on the contractor. An undated South African business blog puts it the same way: wet hire is hiring the equipment with an operator and all that keeps it fully operational, including the diesel.[1][6]
Dry hire is plant hired without the supplier's operator. The same 2020 bid calls it a dry rate where the employer supplies the operator and fuel, and says the contractor still bears the cost of normal maintenance; the employer covers only damage caused directly by the operator's negligence, which the contractor must prove. The blog says the diesel is not included on dry hire: the machine arrives with a full tank and must go back with the same amount.[1][6]
The Cape Winelands District Municipality's plant hire tender, which closed on 19 March 2025, asked for wet rates only: all machines "should be quoted inclusive of fuel, oil and operator as a Wet Rate", and its wet rate "includes fuel, operator, plant, and maintenance (all inclusive)". It describes the wet rate as "the combination of the 'dry rate' and 'diesel rate' per hour" but defines neither of those, so it does not say what a dry rate on its own would cover.[2]
For hourly and daily rates, standing time and what a quote itemises, see the articles on TLB hire prices and the plant hire agreement.[2]
How do South African documents use wet and dry?
The same two words cover different bundles, so each row below gives one document's use, what it puts in the rate and what it leaves out or leaves to the hirer. The rows are municipal documents and one business blog, not a legal standard.[1][2][3][4][6]
| Term and document | In the rate | Outside the rate or left to the hirer | Source |
|---|---|---|---|
| Wet rate, Cape Winelands tender, 2025 | Fuel, oil, operator, plant and maintenance, all inclusive | Establishment, paid separately per one-way kilometre; standby, paid at its own hourly rate | Cape Winelands District Municipality, T 2025/015 |
| Dry rate, Cape Winelands tender, 2025 | Not defined: the tender names it only as one part of the wet rate, with a diesel rate | Not defined; the tender asks for wet rates only | Cape Winelands District Municipality, T 2025/015 |
| Wet rate, George bid PS 012, 2020 | Operator and fuel from the contractor, who also bears the cost of maintenance, servicing and repair | Not stated beyond those inclusions | George Municipality, bid PS 012 of 2020 |
| Dry rate, George bid PS 012, 2020 | The machine, with the contractor bearing the cost of normal maintenance | Operator and fuel, which the employer supplies; the employer covers damage only where the operator's negligence caused it directly and the contractor proves it | George Municipality, bid PS 012 of 2020 |
| Per hour, dry, Siyancuma tariff 2026/27 | The machine for an hour or part of it, out with a full tank | The tank must come back full; the tariff does not say whether an operator is included | Siyancuma Local Municipality, 2026/27 tariffs |
| Wet rate, mini excavator hire request, 2025 | The machine with the supplier's certified operator, fuel kept available and all associated costs | Establishment and de-establishment, asked for as one separate line | Theewaterskloof Municipality, quotation LP 03/2025/26 |
| Wet hire and dry hire, an undated business blog | Wet: the equipment, an operator and what keeps it running, including the diesel. Dry: the equipment, delivered with a full tank | Dry: the operator and the diesel; the machine goes back with as much diesel as it arrived with | A South African business blog, undated |
What should a hire request say about what the rate includes?
Because the documents spell out dry hire differently, or not at all, a request through plant hire should say in words what the rate covers and not rely on the label. The George bid shows why: it asked for wet and dry rates separately where indicated, and said that where a contractor would not offer a dry rate it should enter N/A.[1]
The Contractors Plant Hire Association's standard terms of hire (version 1, 2014) cover the operator in two ways: where plant is supplied with the owner's operator, the operator is under the sole control and supervision of the hirer, who is responsible for the operator's acts or omissions (clause 10.1). Where it is supplied without one, the hirer must supply a competent plant operator licensed where required by law, and carry out the regular daily service of the plant (clause 11). Insurance of the hirer's liability arising from the use or hire of the plant is the hirer's responsibility (clause 14).[5]
Drawing on those documents, a request can name:[1][2][5][4]
- the operator: whether the supplier provides one, and the proof of competency and medical certificate that go with it;[5][7]
- fuel: who supplies it, or whether the machine goes out with a full tank and returns with one, as the Siyancuma tariff states;[2][3][1]
- maintenance and damage: who bears the cost of normal maintenance and of damage, and who must prove it;[1]
- insurance: who insures the machine and the liability, since the George bid had its contractor provide comprehensive insurance on the items normally hired wet and left the items supplied without an operator on its own insurance, and the Association's terms leave the hirer's liability insurance with the hirer;[1][5]
- transport and standby: establishment and de-establishment as their own line, and the standby rate, which the Cape Winelands tender paid separately from the working-time rate.[2][4]
Who checks the operator's papers in wet and dry hire?
Regulation 23(1)(d) of the Construction Regulations, 2014 puts the check on the contractor, which regulation 1 defines as "an employer who performs construction work": the contractor must ensure that mobile plant is operated by a person who "has received appropriate training, is certified competent and in possession of proof of competency and is authorised in writing to operate" it, and who holds a medical certificate of fitness issued by an occupational health practitioner in the form of Annexure 3.[7]
The regulation does not say whose employee the operator is, so calling a hire wet or dry does not settle who checks. On a wet hire, ask for the supplier's operator's papers before the machine starts work; on a dry hire, the hirer's own operator needs them.[7]
A worked example
Take a hypothetical buyer with two quotes for the same excavator, one marked wet and one marked dry, from suppliers whose terms it has not seen. On the terms of the 2020 George bid, the wet quote would carry the operator and fuel, and the dry quote would leave both to the buyer while the supplier still bore normal maintenance. On the terms of the 2026/27 Siyancuma tariff, a dry hour means only that the machine goes out with a full tank and comes back with one; the tariff does not say whether an operator comes with it. The label alone does not settle the operator, so the buyer's reply to both suppliers asks one question: does this hourly rate include the operator, the fuel, maintenance, insurance and transport?[1][3]
Questions buyers ask
What is the difference between wet hire and dry hire?
In the documents read here, wet hire includes the supplier's operator and fuel, and dry hire leaves them to the hirer: George's 2020 bid has the employer supply both on a dry rate. Siyancuma's 2026/27 tariff says only that a dry hour starts and ends with a full tank, and the Cape Winelands 2025 tender names a dry rate without defining it. Ask what the rate covers.[1][3][2][6]
What is a wet rate?
A wet rate is the hourly price of a machine that includes its operator and fuel. The Cape Winelands tender calls it the combination of the dry rate and the diesel rate per hour and says it includes fuel, operator, plant and maintenance; it paid standby at a separate hourly rate.[2]
What work do you need done?
Sources
- George Municipality, Bid PS 012 of 2020: tender for the ad hoc hire of vehicles, plant and equipment if and when required for three years, Closing date 26 February 2021.
- Cape Winelands District Municipality, Tender T 2025/015: the hiring of mechanical and construction plant equipment for the period ending 30 June 2028 (specification and pricing schedules), Closing date 19 March 2025.
- Siyancuma Local Municipality, Tariffs for the 2026/2027 financial year (rental rates for vehicles and equipment), 2026/27 financial year.
- Theewaterskloof Municipality, Quotation LP 03/2025/26: leasing of a 1-ton mini excavator to Grabouw Sportsfield (schedule, special conditions and specifications), 31 October 2025; closing 7 November 2025.
- Contractors Plant Hire Association (CPHA), Terms and conditions of hire (general plant), version 1, Document dated 26 March 2014.
- Leads 2 Business (L2B blog), The importance of dry and wet hire, Undated blog page, read 19 November 2026.
- Department of Labour (Government Gazette 37305), Construction Regulations, 2014 (GN R.84): regulation 23, 7 February 2014.